City still looking for answers from TransEd after Valley Line LRT audit
The city has completed an audit on the Valley Line Southeast LRT project, but it’s not the comprehensive look at delays many on council were hoping for.
The city says it cannot legally audit contractor TransEd for those details.
The line from downtown to Mill Woods is supposed to open this fall.
It's nearly three years behind schedule for a number of reasons, including the discovery of a concrete mass in the riverbank that impacted the Tawatinâ Bridge, labour and material issues during the pandemic, dozens of cracked concrete piers, and faulty cables that needed replacing along the entire 13 kilometre line.
"It is frustrating. We pay for services and we expect for those services to be delivered on time. In this case, Edmontonians have been waiting for three years, and they still continue to wait," said Edmonton Mayor Amarjeet Sohi.
The city has now completed an audit on the Valley Line - including the west section currently under construction.
But it only looks at project oversight - whether the contract is transparent, fair and protects the city’s financial interests and liability.
All the delays are out of scope.
The audit did find city staff have done their due diligence - it makes no recommendations for change.
"Absolutely there's a comfort in knowing that financial interest was protected, that a quality product will be delivered… but they don’t have a product to use yet," Sohi said.
Councillors also heard the city’s relationship with TransEd has been strained over the years.
In 2021 the builder held a press conference about pushing back opening day without first telling the city about the delay.
"It's a continual effort for us to ensure that we have a strong relationship, but it has been a challenging project from that perspective," said interim city manager Adam Laughlin.
Laughlin is working on a major project review, but Sohi is pushing for specific answers on the Valley Line delays.
"I want to know what happened with those pillars. I want to know what happened with those wires, or other delays," he said, adding if city staff can’t work with Trans-Ed to get those answers, he'll ask the province to step in for a comprehensive review.
TransEd sent the following statement to CTV News Edmonton regarding the audit:
"TransEd has always and will continue to partner with the city. This includes reasonable participation in accordance with our contractual obligations and the law in any audit undertaken by the city or other government agency stakeholders."
An official opening date for the Valley Line Southeast LRT has not yet been announced.
CTVNews.ca Top Stories
Prime minister faces mounting pressure to step aside from inside caucus
Prime Minister Justin Trudeau will face mounting pressure from his caucus this week to step down from the leadership of the Liberal party.
Bloc won't hold Liberals 'hostage' over seniors' benefits: cabinet minister
Liberal cabinet minister Steven Guilbeault says the Liberals will not be 'held hostage' by the Bloc Quebecois' demand to expand Old Age Security to more seniors.
Government spending on flights for Canadians fleeing the Middle East unpopular, Nanos survey finds
Amid escalating violence in the Middle East, a majority of surveyed Canadians say they don't believe the costs associated with Canadians fleeing the region should be funded solely by the government.
It's not just Fat Bear Week in Alaska. Trail cameras are also capturing wolves, moose and more
Millions of people worldwide tuned in for a remote Alaska national park’s “Fat Bear Week” celebration this month, as captivating livestream camera footage caught the chubby predators chomping on salmon and fattening up for the winter.
What's behind the northern lights that dazzled the sky farther south than normal
Another in a series of unusually strong solar storms hitting Earth produced stunning skies full of pinks, purples, greens and blues farther south than normal, including into parts of Germany, the United Kingdom, New England and New York City.
How psilocybin, the psychedelic in mushrooms, may rewire the brain to ease depression, anxiety and more
Small clinical trials have shown that one or two doses of psilocybin, given in a therapeutic setting, can make dramatic and long-lasting changes in people suffering from treatment-resistant major depressive disorder, which typically does not respond to traditional antidepressants.
Children and adults transported to a Pennsylvania hospital after ingesting 'toxic mushrooms'
Children and adults were transported to a hospital in Pennsylvania Friday night after being sickened by mushrooms, authorities said.
When Europe's railroad dining cars were the height of luxury
The Orient Express' opulent passenger experience was later immortalized in popular culture by authors like Graham Greene and Agatha Christie. But dining on the move was very much a triumph of logistics and engineering.
As Hezbollah and Israel battle on the border, Lebanon's army watches from the sidelines
Since Israel launched its ground invasion of Lebanon, Israeli forces and Hezbollah militants have clashed along the border while the Lebanese army has largely stood on the sidelines.