City still looking for answers from TransEd after Valley Line LRT audit
The city has completed an audit on the Valley Line Southeast LRT project, but it’s not the comprehensive look at delays many on council were hoping for.
The city says it cannot legally audit contractor TransEd for those details.
The line from downtown to Mill Woods is supposed to open this fall.
It's nearly three years behind schedule for a number of reasons, including the discovery of a concrete mass in the riverbank that impacted the Tawatinâ Bridge, labour and material issues during the pandemic, dozens of cracked concrete piers, and faulty cables that needed replacing along the entire 13 kilometre line.
"It is frustrating. We pay for services and we expect for those services to be delivered on time. In this case, Edmontonians have been waiting for three years, and they still continue to wait," said Edmonton Mayor Amarjeet Sohi.
The city has now completed an audit on the Valley Line - including the west section currently under construction.
But it only looks at project oversight - whether the contract is transparent, fair and protects the city’s financial interests and liability.
All the delays are out of scope.
The audit did find city staff have done their due diligence - it makes no recommendations for change.
"Absolutely there's a comfort in knowing that financial interest was protected, that a quality product will be delivered… but they don’t have a product to use yet," Sohi said.
Councillors also heard the city’s relationship with TransEd has been strained over the years.
In 2021 the builder held a press conference about pushing back opening day without first telling the city about the delay.
"It's a continual effort for us to ensure that we have a strong relationship, but it has been a challenging project from that perspective," said interim city manager Adam Laughlin.
Laughlin is working on a major project review, but Sohi is pushing for specific answers on the Valley Line delays.
"I want to know what happened with those pillars. I want to know what happened with those wires, or other delays," he said, adding if city staff can’t work with Trans-Ed to get those answers, he'll ask the province to step in for a comprehensive review.
TransEd sent the following statement to CTV News Edmonton regarding the audit:
"TransEd has always and will continue to partner with the city. This includes reasonable participation in accordance with our contractual obligations and the law in any audit undertaken by the city or other government agency stakeholders."
An official opening date for the Valley Line Southeast LRT has not yet been announced.
CTVNews.ca Top Stories

'No one else has done this on the planet': Guilbeault insists emissions cap delay is due to novelty
Environment and Climate Change Minister Steven Guilbeault says the delay in announcing details of his government’s proposed oil and gas sector emissions cap is due to its uniqueness and to wanting to get it right.
Buckingham Palace releases this year’s Christmas card
Buckingham Palace released an image of the Christmas card that King Charles III and Queen Camilla will be sending out this year.
Canada has a secretive history of adoption, and some want it brought to light
In a theatre in St. John's, N.L., a murmur spreads through the audience as people timidly raise their hands. They have been asked if they saw their own stories reflected in the film they just watched -- 'A Quiet Girl.'
'People are confused': Survey suggests Canadians need education on Charter rights
While one-third of Canadians say they have read the Charter of Rights and Freedoms, many fail to distinguish between its text and that of the U.S. Declaration of Independence, a new survey suggests.
A gigantic new ICBM will take U.S. nuclear missiles out of the Cold War-era but add 21st-century risks
The $96 billion Sentinel overhaul involves 450 silos across five states, their control centres, three nuclear missile bases and several other testing facilities. The project is so ambitious it has raised questions as to whether the Air Force can get it all done at once.
Marathon Conservative carbon tax filibuster ends after nearly 30 consecutive hours of House votes
The Conservative-prompted filibuster in the House of Commons ended Friday night, after MPs spent nearly 30 hours voting non-stop on the government's spending plans.
Tennessee residents clean up after severe weekend storms killed 6 people and damaged neighbourhoods
Central Tennessee residents and emergency workers cleaned up Sunday from severe weekend storms and tornadoes that killed six people and sent more to the hospital while damaging buildings, turning over vehicles and knocking out power to tens of thousands.
Elon Musk restores X account of conspiracy theorist Alex Jones
Elon Musk has restored the X account of conspiracy theorist Alex Jones, pointing to a poll on the social media platform formerly known as Twitter that came out in favour of the Infowars host who repeatedly called the 2012 Sandy Hook school shooting a hoax.
Woman charged with manslaughter after 2 sets of young twins killed in 2021 U.K. fire
A woman has been charged with four counts of manslaughter after two sets of young twins were killed in a fire that ripped through a London home in 2021.