Edmonton's newest LRT Line expected to be running by late 2021
The company tasked with building and maintaining Edmonton's latest addition to its light rail transit network has released a more precise completion target for the southeast Valley Line LRT.
In an interview with CTV News Edmonton on Monday, an official for TranEd said the $1.8-billion project has now reached its safety and communications systems testing phase and that he expects the new line will be operational by late 2021.
"Right now we’re looking at a year delay from the original date," said TransEd spokesperson Dallas Lindskoog.
"We've got a team of individuals testing every single component of the system that we built," he said. "Most of them are installed now, so they're testing those wires and the connectivity."
The roughly two-dozen trains are all in place for the low-floor transit system. The track has been laid - but the finer details are still in the works.
Lindskoog said the Tawatinâ Bridge, which crosses the North Saskatchewan River, is "progressing nicely."
"We've gotten past the actual construction of the concrete work, the cables, all of that is complete," he said. "The rail is across the bridge, all the overhead catenary system that you see… is installed."
Up next for that section, said Lindskoog, is the bridge's underslung shared-use path and the reestablishment of the trail network in the river valley.
"In order to get that done though we've still got some work to do in the parks," he said. "We've got to reestablish Louise McKinney Park and Henrietta Muir Park as well."
The new line's twin tunnels' southern portal is located at Louise McKinney Park.
According to Lindskoog, TransEd has a "contractural requirement" to complete the bridge's pedestrian walkway, as well as cosmetic features such as landscaping, before launching the new LRT line for public use.
"We don't want a whole bunch of leftover work as well," he said. "We want the system completely turned over. All of the roads, all of the landscaping, all of the rail – when the train goes into operation."
Originally slated to open by the end of 2020, construction on the 13.1-kilometre line has met its share of challenges.
The first major snag came in 2018, when construction crews encountered a large concrete mass in the North Saskatchewan riverbed. That discovery meant work on the Valley Line's Tawatinâ Bridge was delayed and caused subsequent ripple effects on the rest of the project.
DELAYS DUE TO COVID-19: TRANSED
"We've been trying to make up time since that encounter with the concrete," said Lindskoog, "and then the pandemic landed. We've been trying to make up for some of the efficiencies that we've lost there."
"Working with a mask on, working and maintaining distance is challenging," he said.
Lindskoog pointed to worker absenteeism due to pandemic-related family issues as one cause of construction delays.
"We've had very little positive cases of COVID on the project," he added.
According to the TransEd spokesperson, the project also faced supply issues for building materials because of COVID-19.
FINISHING TOUCHES
One major aspect of the southeast Valley Line is the twin tunnels that runs from 102 Avenue and 96 Street to Louise McKinney Park, beneath Edmonton's Quarters district.
Lindskoog said finishing touches are being completed on those, as well as the elevated platform known as Davies Station – which will include a full Park & Ride and a transit centre.
The TransEd spokesperson believes, once complete, his company's signaling system won't face any of the hiccups that plagued Edmonton's Metro LRT line in 2017.
Assuming there are no further setbacks, by 2022, Edmontonians can expect the 11-stop electric rail line to be available to transport them from millwoods to the city's downtown – and vice versa – in about 30 minutes.
TransEd will begin testing trains on Connors Hill and the new Tawatinâ Bridge this summer.
The $1.64-billion Stage 2 of the Valley Line LRT will see construction of the west section which will run from 102 Street to Lewis Farms.
With files from CTV News Edmonton's David Ewasuk
CTVNews.ca Top Stories
For years she thought her son had died of an overdose. The police video changed all that
Austin Hunter Turner died in 2017, on a night that his mother has rewound and replayed again and again, trying to make sense of what happened.
Niagara Region 'proactively' declares state of emergency ahead of total solar eclipse
Niagara Region says it has declared a state of emergency 'out of an abundance of caution' as it prepares for an influx of visitors for next month’s total solar eclipse.
This historical tavern in Toronto is closing after nearly 200 years
An historic downtown Toronto bar is closing its doors next week after nearly 200 years in business.
Social media can alter children's brains and impact mental health: neuroscientist
Neuroscientist Emma Duerden says social media can alter children's brains and have negative impacts on their mental health.
Ontario homeowner on the hook for $27,000 when contractor severed power line
An Ontario man who built a garage on his property has been locked in a battle with his electricity provider for a year and half over a severed power line.
Montreal doctors' breakthrough discovery about causes of cerebral palsy giving hope
A breakthrough discovery made by doctors at the Montreal Children's Hospital about the causes of cerebral palsy is giving new hope to one West Island family.
Edmonton broadcasting giant Bruce Hogle dead at 95
An Edmonton broadcasting pioneer has passed away.
Feeling older than you are? It could be how you sleep
Not getting enough sleep may cause you to feel five to 10 years older than you really are, according to two new studies.
CRA no longer requiring 'bare trust' reporting in 2023 tax return
The Canada Revenue Agency announced Thursday it will not require 'bare trust' reporting from Canadians that it introduced for the 2024 tax season, just four days before the April 2 deadline.