Southeast LRT delays caused by cracks on piers 'deeply disappointing': mayor
The Valley Line Southeast LRT will not open this summer as planned.
The CEO of TransEd announced at Davies Station on Wednesday cracks had been found on three concrete piers that support the elevated tracks.
After further investigation, the company found a total of 18 piers that "may require strengthening."
"This issue will unfortunately delay the service commencement," TransEd CEO Ronald Joncas said. "We understand the disappointment and frustration…we were all anticipating and getting ready for the opening of the Valley Line Southeast LRT this summer. Sadly, this will not be possible.
"Once our engineering have completed the design to strengthen the pier and our construction experts have determined the additional construction work required, we will be in a better position to announce the target service commencement date."
The CEO said he's disappointed and apologized to Edmontonians. Joncas added there's no risk to the public and that it's safe to walk and drive under elevated sections along the LRT route.
DELAYS AND DISAPPOINTMENT
Construction started in 2016 and the route was scheduled to open in December 2020, but crews found a large concrete mass under the now open Tawatinâ Bridge in 2018 that delayed construction for months. Officials then delayed the opening date to within 2021, the end of 2021 and summer 2022.
Edmonton Mayor Amarjeet Sohi said the latest delays are "frustrating and deeply disappointing."
"TransEd has not delivered this project as expected. They are responsible for this delay and they will be held accountable to get the work completed and open a line that is safe to ride."
The Valley Line Southeast LRT is a public-private partnership, or P3, between Edmonton and TransEd, Sohi and City Manager Andre Corbould explained. The federal and provincial government also provided funding for the project.
When contracts were signed, the city expected to save about $500 million through the P3, Corbould said.
"We buy a product, we don't design it, we don't engineer it and we don't build it ourselves. Specialists do that," Corbould explained.
Other large projects such as the Walterdale Bridge, the 102 Avenue Bridge and the Metro Line LRT experienced years of issues and delays before they opened.
On Wednesday, Sohi asked administration for a comprehensive review on how the city builds such projects.
Corbould said TransEd will cover the financial costs of the delays.
CTVNews.ca Top Stories
Grandparent scam: London, Ont., senior beats fraudsters not once, but twice
It was a typical Tuesday for Mabel Beharrell, 84, until she got the call that would turn her world upside down. Her teenaged grandson was in trouble and needed her help.
Deaths of 4 people on Sask. farm confirmed as murder-suicide
The deaths of four people on a farm near the Saskatchewan village of Neudorf have been confirmed a murder-suicide.
George Washington family secrets revealed by DNA from unmarked 19th century graves
Genetic analysis has shed light on a long-standing mystery surrounding the fates of U.S. President George Washington's younger brother Samuel and his kin.
Why some Christians are angry about Trump's 'God Bless the USA' Bible
Former U.S. President Donald Trump is officially selling a copy of the Bible themed to Lee Greenwood’s famous song, 'God Bless the USA.' But the concept of a Bible covered in the American flag has raised concern among religious circles.
Full parole granted to man convicted in notorious 'McDonald's murders' in Cape Breton
The Parole Board of Canada has granted full parole to one of three men convicted in the brutal murders of three McDonald's restaurant workers in Cape Breton more than 30 years ago.
Rainfall warnings of up to 80 mm among weather alerts in effect for 6 provinces
Rainfall warnings of up to 90 millimetres and other alerts have been issued for six Canadian provinces, according to the latest forecasts.
Sunshine list: These were the Ontario public sector's highest earners in 2023
Ontario released its annual sunshine list Thursday afternoon, noting that the largest year-over-year increases were in hospitals, municipalities, and post-secondary sectors.
Bus plunges off a bridge in South Africa, killing 45 people. An 8-year-old child is only survivor
A bus carrying worshippers headed to an Easter festival plunged off a bridge on a mountain pass and burst into flames in South Africa on Thursday, killing at least 45 people, authorities said.
Calgary bridges remain closed due to ongoing police incident
Calgary police have shut down a number of bridges into and out of the downtown core as officers deal with a distraught individual.