'We will dig deeper': Questions abound over delay plagued Valley Line LRT and the P3 model
Yet another delay to the opening of the Valley Line Southeast LRT has some questioning the value that public-private partnership (P3) infrastructure projects have, with the city pledging a comprehensive review into the practice.
On Wednesday, the CEO of TransEd announced that cracks on three concrete piers supporting elevated tracks along the new LRT line would delay the opening of the project indefinitely, with another 18 piers that "may require strengthening."
Construction on the project started in 2016, with the route initially scheduled to open in December 2020. A "large concrete mass" was discovered under the Tawatinâ Bridge in 2018 that set construction back for months.
That bridge opened in December 2021, but the Valley Line opening was pushed back to within 2021, then the end of 2021, and summer 2022. In an update in December 2021, TransEd indicated that around 96 per cent of the construction for the 13-kilometre LRT leg was completed.
Edmonton Mayor Amarjeet Sohi said the latest delays were "frustrating and deeply disappointing."
"We will dig deeper into the root causes, and TransEd needs to be held accountable because that is a basic engineering design that companies have been doing for decades and decades," Sohi said Wednesday. "Obviously, as part of our process to hold TransEd accountable for this project, we will dig deeper into that."
"I hope that TransEd will be able to come back to us quickly on what they are going to do to fix those deficiencies and fix them in a permanent way, that we have a safe system to rely on," Sohi added.
The LRT extension to Mill Woods is a public-private partnership (P3) involving the city and TransEd, with the federal and provincial governments providing funding.
Orders of government and private sector partners work together through the P3 model to build public infrastructure, with taxpayers owning the infrastructure but private companies designing, building, maintaining and operating the project.
According to the Canadian Council for Public-Private Partnerships, the P3 model is a proven alternative to building new infrastructure projects that "can be delivered sooner" and "more cost-effectively" than if orders of government managed the whole contracting and building phases.
Steve Bradshaw, union president representing Edmonton transit workers, said should the project have gone ahead without the use of the P3, the LRT line would be operational.
"Without proper oversight, we get sub-standard work and substandard building materials, and the bills keep adding up," Bradshaw said in a statement. "When will it ever stop?"
"We have been driving across the Low Level Bridge, the High Level Bridge on concrete pillars and they are perfectly safe," he added in an interview with CTV News Edmonton. "What's going on here?"
'TORTURED BUSINESS MODEL'
The city expected to save around $500 million by using the P3 model, Corbould explained Wednesday, adding that the city buys the product but doesn't design or engineer it.
The Amalgamated Transit Union Local 569 president said P3 projects create conditions where competing contractors outbid each other by "low-balling" and offering "false promises."
"It's a tortured business model," Bradshaw said. "There's five or six different corporate entities involved in that."
"(It's) impossible to tell who's responsible for what," he added. "Then riders suffer from the delays and taxpayers end up footing the bill."
In the meantime, Bradshaw hopes the city adds more bus service along the Valley Line route to meet the growing demands of transit users.
"It's desperately needed," he said, "to fill out the system properly."
BUSINESS SUPPORT
For the Edmonton Chamber of Commerce, the LRT delay was disappointing as more businesses along the route would be further inconvenienced and impacted by construction, and all the detours and traffic disruptions it causes.
"With the rising inflation costs, the impact the construction has had to businesses along the line, and labour shortages that are ongoing, the delay of this project is deeply frustrating to our members and the broader business community," the Chamber said in a statement.
Additionally, the Chamber of Commerce said it wants the city to explore how it can better support businesses impacted by major construction projects that make it more difficult for customers to patronize their establishments.
"While it is comforting to hear that the P3 fixed price model used to build the Valley Line LRT has saved the city from taking direct fiscal impact of this delay, the indirect costs of the delay cannot be as easily quantified."
'A VERY DIFFERENT WORLD'
Bradshaw pointed to the long-standing signaling issues on the LRT expansion to NAIT that ended with the city firing that contractor.
"It took over and over and over again until the city finally said, enough, get them out of here and do it ourselves and get it done right," he said. "Ever since then, we've had it up and running."
"The mayor and city manager were there yesterday saying, well, you know this is a learning experience," he added. "When do we take the learning experience and implement it?"
Andrew Knack, councillor for Ward Nakota Isga, says the city has, learned its lessons and moved to a new project management system for the Valley Line West LRT expansion.
The second stage of the Valley Line will eventually connect Lewis Farms in west Edmonton to the downtown core, and complete the southeast leg to Mill Woods.
Coun. Andrew Knack speaks to CTV News Edmonton in front of Valley Line West construction on Thursday, Aug. 11, 2022 (CTV News Edmonton/Jeremy Thompson).
Knack says the southeast LRT extension was approved under an old management system that was revamped following the Metro Line expansion and Groat Road Bridge rehabilitation project delays.
"This is a very different world today, and the projects that we are building today are on a very different system than what we used to have years ago," Knack told CTV News Edmonton.
The Valley Line West is a "modified" P3 arrangement, which is "not quite the same system" as what the city has with TransEd, Knack added.
"We do have more control in that project than what we see in the Valley Line Southeast," he said. "The way we've built the contracts has more control for the city and more oversight."
With files from CTV News Edmonton's Diego Romero and Jeremy Thompson
CTVNews.ca Top Stories
BREAKING Trudeau promises $1B in loans for child-care providers to expand care centres
The federal government is launching a new loan program to help child-care providers in Canada expand their spaces, and will be extending further student loan forgiveness and training options for early childhood educators, Prime Minister Justin Trudeau announced Thursday.
Spring allergy season has begun. Where is it worse in Canada?
The spring allergy season has started early in many parts of Canada, with high levels of pollen in some cities already. Experts weigh in on which areas have it worse so far this season.
Ontario reveals highest public sector salaries in sunshine list
Ontario released its annual sunshine list Thursday afternoon, noting that the largest year-over-year increases were in hospitals, municipalities, and post-secondary sectors.
Several flight attendants from Pakistan have gone missing after landing in Canada
Multiple flight attendants from Pakistan International Airlines have abandoned their jobs and are believed to have sought asylum in Canada in the past year and a half, a spokesperson for the government-owned airline says.
N.B. man wins $64 million from Lotto 6/49
A New Brunswicker will go to bed Thursday night much richer than he was Wednesday after collecting on a winning lottery ticket he let sit on his bedroom dresser for nearly a year.
'Nonsense:' Doug Ford slams lawsuits filed by Ontario school boards against social media platforms
Premier Doug Ford says that lawsuits launched by four Ontario school boards against a trio of social media platforms are “nonsense” and risk becoming a distraction to the work that really matters.
Multiple bridges in Calgary shut down for police incident
Calgary police have shut down a number of bridges into and out of the downtown core as officers deal with a distraught individual.
King Charles calls for acts of friendship in first public remarks since Kate's cancer diagnosis
King Charles III gave public remarks for Maundy Thursday, addressing the importance of acts of friendship, following his and Catherine, Princess of Wales’ cancer diagnoses.
Fallen crypto mogul Sam Bankman-Fried sentenced to 25 years in prison
Crypto entrepreneur Sam Bankman-Fried was sentenced Thursday to 25 years in prison for a massive fraud that unravelled with the collapse of FTX, once one of the world's most popular platforms for exchanging digital currency.