Southeast LRT delays caused by cracks on piers 'deeply disappointing': mayor
The Valley Line Southeast LRT will not open this summer as planned.
The CEO of TransEd announced at Davies Station on Wednesday cracks had been found on three concrete piers that support the elevated tracks.
After further investigation, the company found a total of 18 piers that "may require strengthening."
"This issue will unfortunately delay the service commencement," TransEd CEO Ronald Joncas said. "We understand the disappointment and frustration…we were all anticipating and getting ready for the opening of the Valley Line Southeast LRT this summer. Sadly, this will not be possible.
"Once our engineering have completed the design to strengthen the pier and our construction experts have determined the additional construction work required, we will be in a better position to announce the target service commencement date."
The CEO said he's disappointed and apologized to Edmontonians. Joncas added there's no risk to the public and that it's safe to walk and drive under elevated sections along the LRT route.
DELAYS AND DISAPPOINTMENT
Construction started in 2016 and the route was scheduled to open in December 2020, but crews found a large concrete mass under the now open Tawatinâ Bridge in 2018 that delayed construction for months. Officials then delayed the opening date to within 2021, the end of 2021 and summer 2022.
Edmonton Mayor Amarjeet Sohi said the latest delays are "frustrating and deeply disappointing."
"TransEd has not delivered this project as expected. They are responsible for this delay and they will be held accountable to get the work completed and open a line that is safe to ride."
The Valley Line Southeast LRT is a public-private partnership, or P3, between Edmonton and TransEd, Sohi and City Manager Andre Corbould explained. The federal and provincial government also provided funding for the project.
When contracts were signed, the city expected to save about $500 million through the P3, Corbould said.
"We buy a product, we don't design it, we don't engineer it and we don't build it ourselves. Specialists do that," Corbould explained.
Other large projects such as the Walterdale Bridge, the 102 Avenue Bridge and the Metro Line LRT experienced years of issues and delays before they opened.
On Wednesday, Sohi asked administration for a comprehensive review on how the city builds such projects.
Corbould said TransEd will cover the financial costs of the delays.
CTVNews.ca Top Stories
Trudeau acknowledges charges in Nijjar killing, calls for commitment to democracy
Prime Minister Justin Trudeau has acknowledged the charges laid Friday in relation to the murder of B.C. Sikh activist Hardeep Singh Nijjar.
No proof man lied to brother about number of kittens born in litter, B.C. tribunal rules
A man was denied a $5,000 payout from his brother after a B.C. tribunal dismissed his claim disputing how many kittens were born in a litter.
Bodies recovered in Mexico likely 2 Australians, 1 American who went missing: officials
Three bodies recovered in an area of Baja California are likely to be those of the two Australians and an American who went missing last weekend during a camping and surfing trip, the state prosecutor’s office said Saturday.
Princess Anne lays wreath at B.C. veteran's cemetery; receives 21-gun salute
Princess Anne paid tribute to veterans buried at a cemetery in British Columbia today, laying a wreath to honour the more than 2,500 military personnel and family members buried there.
Mystik Dan wins the 150th Kentucky Derby at Churchill Downs in a three-horse photo finish
Mystik Dan won the 150th Kentucky Derby in a photo finish, edging out Forever Young and Sierra Leone for the upset victory.
'I just can't believe that it took so long': Body found in wreckage 3 months after deadly fire
A man accused of arson in a January Old Strathcona apartment fire is expected to be charged with manslaughter after a body was discovered in the burned building late last month.
Quebec police hand out hundreds of tickets to Hells Angels and other bikers before 'first run' meeting
Quebec provincial police handed out hundreds of fines to Hells Angels members and other supporting motorcycle clubs who met for their 'first run' in a small town near Sherbrooke, Que.
Work stoppage possible as WestJet issues lockout notice to maintenance engineers' union
A lockout notice issued by WestJet to a union representing aircraft maintenance engineers could result in a work stoppage next week.
London Drugs begins 'gradual reopening' on 7th day after cyberattack
Almost a week after all London Drugs stores across Western Canada abruptly closed amid a cyberattack, they began a "gradual reopening" on Saturday.